Rooftop Steel Frame in Stoneybatter
Steel frame for a rooftop extension built off a concrete slab, with braced portals, purlin cleats and hot dip galvanised fixings set out to take a lightweight roof over the existing building.
About this structural steel project
Steel frame for a rooftop extension built off a concrete slab, with braced portals, purlin cleats and hot dip galvanised fixings set out to take a lightweight roof over the existing building.
The steel was fabricated in our Dublin workshop and installed on site in Stoneybatter, Dublin 7 by our own team. Every job is set out from measured site dimensions, welded and finished in house, and delivered to suit the site programme.
Why we built it this way
Building on top of an existing building is all about weight and fixings. The frame was kept light, braced to stop it racking, and set out so the new roof bears onto the slab where the engineer wanted it. Galvanised fixings were used because they sit in the roof build up for good and cannot be got at again once it is closed in.
Planning something similar? See our Structural Steel Fabrication service in Dublin or ask us for a free quote.
How we work on jobs like this
- Step 1
Site measure and drawings
We visit, take measurements and agree sizes, finishes and fixing details before anything is cut.
- Step 2
Workshop fabrication
Cutting, drilling, forming and welding is carried out in our own workshop under EN 1090-1 EXC3 and ISO 9001:2015 certification.
- Step 3
Finishing
Primed, painted, powder coated or hot dip galvanised to suit the exposure and the look you want.
- Step 4
Delivery to site
Delivered and installed on an agreed date, with lifting arranged where the steel needs craning in.
Similar structural steel projects

Colonnade Steelwork, Apartment Development
Long run of red oxide primed columns and beams forming the colonnade and canopy steel to a new apartment and retail development, craned in and bolted off the precast structure bay by bay.
View Colonnade Steelwork, Apartment Development case study
Internal Steel Mezzanine Frame
Two tier steel frame erected inside a working industrial unit to form an office mezzanine, with bolted moment connections, base plates resin fixed to the slab and a clean edge for decking.
View Internal Steel Mezzanine Frame case study
Portal Frames, Housing Scheme
Run of red oxide primed portal frames fabricated and erected across a new housing scheme, each frame bolted to cast in base plates over rising block work.
View Portal Frames, Housing Scheme case studyWant something similar for your project?
Send us drawings, a sketch or a site photo. We come back with a fixed price and a firm lead time, usually within one working day.